Lightbridge targets mid-2030s lead test assemblies via DOE-backed SHED pilot plant at INL
Reuters2026/09/08 11:04- Lightbridge set a two-track commercialization plan to accelerate Lightbridge Fuel deployment, following selection for DOE’s Launch Pad INL program.
- SHED pilot facility at Idaho National Laboratory targets Lead Test Assemblies under DOE authorization, aiming for mid-2030s loading in commercial reactors.
- LEFF commercial-scale plant will advance separately through NRC licensing, with SHED operations intended to shorten licensing timelines.
- Management expects existing cash resources to cover SHED construction, operations, and decommissioning; detailed cost estimates remain in development.
- Commercial rollout goal targets large-scale use by 2040, supported by planned utility benefits from higher capacity factors, power uprates, and safety margins.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Storage Giant Offers Huge Bonuses Again: Micron Awards Up to 68 Months’ Bonus
Micron Technology has announced record-breaking bonuses for its employees in Taiwan, ranging from 35 to 68 months’ salary, with a minimum cash compensation of 1.7 million New Taiwan dollars. However, the Taoyuan union, representing about two-thirds of Micron’s workers in Taiwan, has refused to accept the offer, insisting that 15% of operating profits be included in the bonus distribution and maintaining the threat of a strike.

Dogecoin ETF Closure Sets October Exit for Bitwise BWOW Holders