Wallbridge Mining Presents Fenelon Gold Project Plan Targeting 107,000 Ounces Annually
Bitget2026/10/16 17:04- Wallbridge Mining plans to complete the Fenelon pre-feasibility study by late 2027 or early 2028, funded by an approximately CAD 56 million private placement.
- Cash and cash equivalents totaled approximately CAD 74 million at June 30, 2026.
- Fenelon's preliminary economic assessment estimates an after-tax net present value of CAD 706 million at a 5% discount rate.
- Initial capital is estimated at CAD 579 million, with average annual production of 107,000 gold ounces over a 16-year mine life.
- The assessment projects a 21% after-tax internal rate of return using a USD 2,200-per-ounce gold price.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
New York Federal Reserve Survey: Service Sector Price Increases Hit Fastest Pace Since 2022, Business Activity Index Drops to Lowest Since March
A survey released by the New York Fed on Friday shows that in October, sales prices for service sector firms increased at the fastest pace since 2022, with input costs remaining robust and supply conditions continuing to deteriorate. Businesses’ pessimism about the commercial outlook has significantly intensified, with the overall business activity index falling by 12 points from the previous month to minus 20.7, marking the weakest reading since March.

Raoul Pal Holds Bitcoin, Solana and Ethereum, but Calls One Wildly Undervalued
Ethos Technologies President Wang Lingke Reports Sale of $4.54 Million in Common Shares
Exclusive report - Boeing memorandum says sales chief McMullen will retire