Pulse Oil plans Bigoray well restart to boost production
Bitget2026/11/06 13:01- Pulse Oil is starting work at its wholly owned Bigoray Nisku E pool to boost production, targeting completion by year-end 2026.
- Existing working capital will fund the program, which aims to generate cash flow for sustained Nisku D pool solvent injection.
- Plans include restarting an oil well and converting a suspended well for water injection to support pressure ahead of eventual solvent flooding.
- A roughly 1,900-meter connecting pipeline has regulatory approval; installation is expected to start within weeks and take about 20 days.
- D pool solvent injection was temporarily suspended because of working capital constraints and rising solvent costs.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Ethereum co-founder recommends synchronous composability technology

After many years, Apple plans to relaunch its charity collaboration with (RED), introducing special edition HomePod mini 2 and AirPods Max 2.
This will be Apple's first Product(RED) hardware release in over two years since the 2023 Apple Watch Series 9. The HomePod mini 2 will feature a red mesh exterior, with its overall design remaining consistent with the existing version, differing only in color. The AirPods Max 2 will return with a silver body, paired with white mesh ear cushions, a white headband, and a multifunctional control knob in red.

Quant’s multichain Rollup Fusion mainnet is now open to the public