Lithium Americas presents Thacker Pass plan targeting mechanical completion in late 2027
Bitget2026/11/12 12:37- Lithium Americas targets mechanical completion of Thacker Pass Phase 1 in late 2027, with production ramp-up through 2028.
- Nominal annual capacity is 40,000 tonnes of battery-quality lithium carbonate; 2029 is targeted as the first full-capacity production year.
- Detailed engineering is complete; procurement is more than 90% complete.
- Advances received under the $2.23 billion U.S. Department of Energy ATVM loan total $1.45 billion.
- General Motors holds a 20-year offtake agreement covering up to 100% of Phase 1 production.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like

Full Statement from Nvidia Regarding Jensen Huang's Resignation and Leadership Team Restructuring
On the 12th, the board of directors announced that Jensen Huang has resigned from his positions as President, CEO, and board member, effective immediately. Current Executive Vice President and CFO Colette Kress has agreed to serve as interim CEO. The board has initiated a formal search for a new CEO and will consider candidates both inside and outside the company. At the same time, the board has appointed Harvey C. Jones as its first-ever Chairman.